GTC to start developing City Rose Park offices in 2019

19 November 2018

Globe Trade Center is scheduled to break ground on City Rose Park on Bulevardul Expoziţiei in Bucharest next year. The investment will include three office buildings, with costs estimated at €100m. The first two buildings to go up next year will offer 18,300 sqm and 17,200 sqm respectively. The third building, with 14,500 sqm of space, is in the pre-planning stage. The first two buildings are scheduled to be delivered in mid-2021, and the third is set for completion in the first half of 2022.