The association formed by CCN Altyapi Atirimlari and CCN Hastane Hizmetleri, both from Turkey, won a tender for the design of the new headquarters of the MAI Hospital “Prof. Dr. Dimitrie Gerota” in the Capital, located in Aleea Privighetiloril 1A, sector 1. With a budget of RON 1.55 billion, excluding VAT, the contract was awarded for the amount of RON 1.24 billion, excluding VAT. Funding will be provided through the National Recovery and Resilience Plan (PNRR).
The contract will run for a period of 42 months, of which 9 months for the design activity, including the reception of the technical project, and 33 months for the work execution activity, including the provision of devices and equipment, but also the reception at the end of the works, but no more no later than June 30, 2026.
Source: Profit.ro